
A five-page website usually takes two to four weeks from kickoff to launch. An eight-page site runs three to five weeks, and a twenty-page ecommerce store typically takes six to ten weeks once product capture and payment setup are counted.
The build itself is rarely what holds a project up. Copy, photos, product data and a single clear decision-maker decide most launch dates. Here is where the weeks actually go, what each package realistically needs, and how to keep a project on schedule.
What are the stages of a website build?
A website moves through the same six stages whether it has five pages or twenty: kickoff, content, design, build, review and launch. Only two of those stages involve someone sitting at a screen making the site. The rest are decisions, and decisions are where dates slip.
On a five-page brochure site, design and build together usually account for about two weeks of working time. The other two weeks go to waiting: text, photos, logo files, feedback. If your content lands in week one, you launch in two weeks. If it lands in week four, you launch in week six, with exactly the same amount of design work completed.
- Kickoff and sitemap: which pages exist, what each must do, who signs off. A day or two.
- Content and photos: one to three weeks, and the stage you control most directly.
- Design: three to seven working days for a five-page site, longer for custom layout work.
- Build and CMS setup: about a week for five pages, two weeks for eight.
- Review: two rounds of changes, each taking a few working days.
- Launch: domain, DNS, email and SSL, usually one to three days.
How long does a website take to build by page count?
Page count matters less than page type. Five pages of standard layout, in the region of home, about, services, gallery and contact, is a short build. Eight pages with a blog, team profiles and a booking form means more layouts and more sign-off. A twenty-page store adds product capture, categories, delivery rules and a payment gateway such as PayFast or Yoco, which is why stores take roughly twice as long as the biggest brochure site.
The ranges below are what we quote from when you ask for a website design package, and they assume content arrives on schedule. Every plan is billed monthly with no upfront build fee, so the amount you pay does not change if a project runs a week longer. Your launch date does. If monthly cost is your first question, the package prices are set out in full.
Why do content and photos decide the launch date?
Content is the stage that runs over, and it is usually planned last. A five-page site needs somewhere between 400 and 700 words a page, photos that stay sharp on a high-resolution screen, and a logo in a format a designer can work with. None of that is difficult. All of it competes with running the business, which is why it arrives late.
Photos are the sticking point more often than words. Pictures taken under office downlights and cropped square look acceptable on a handset and poor on a laptop. Since much of your traffic arrives on a phone, that matters less than most people assume, but the desktop view is still the one clients screenshot. Book a photographer before kickoff rather than during build. If stock images are the plan, choose them in week one so layouts are built around the right crops.
Store products are the same problem at larger scale. Fifty products, each with a title, price, description and three photos, is a week of data entry for one person. Decide early who does that work, and whether it happens before or after the design is approved.
Why do website projects run late?
Late launches are seldom a design failure. They come from missing content, too many approvers, pages added mid-build and the assumption that going live is a five-minute switch. A five-page site that quietly becomes eight pages is a different project with a different date, and working weekends is not the fix.
Most of it is settled before kickoff. The rest is settled by writing dates down and holding to them. Extra pages are not a problem when they are priced and scheduled, and the standard add-on for one is R20 per page per month, but they do move the launch.
- One person gives final approval. Feedback from five people is not feedback, it is a meeting.
- A content deadline in the schedule, with the launch date moving if it slips.
- Photos, logo files and brand colours sent in week one, not when design starts.
- A frozen page list at kickoff, with later pages treated as a scheduled change.
- Two review rounds, both booked in advance, so feedback does not sit for a week.
What happens on launch day with DNS and email?
Launch takes less time than people expect, provided the domain and email are handled in the right order. A new .co.za domain is registered and pointed at the server. An existing domain keeps its records until the new site has been tested on a temporary address, and only then are the records switched across.
Email is the part to plan. Moving mailboxes without warning loses mail that arrives mid-switch. Create the new mailboxes first, forward from the old ones, then change DNS. Propagation usually takes a few hours and occasionally up to 48, so warn staff that a message may land in either inbox for a short window. Keep the old mailboxes alive until everything has settled.
Load-shedding is the other local factor. Hosting and email on a server in your office go down with the power; a site on Techadon Cloud does not depend on your building's supply, and the firewall, CDN, monitoring and automated backups are already running before you launch. Migrating an existing site across is done at no charge, which usually removes the last reason to delay.
| Package | Pages | Typical timeline | What sets the pace |
|---|---|---|---|
| Starter, R300/mo | 5 | 2 to 4 weeks | Copy and photos |
| Basic, R400/mo | 5 with CMS | 2 to 4 weeks | Copy, photos, CMS handover |
| Business, R600/mo | 8 with CMS | 3 to 5 weeks | More layouts, more sign-off |
| Business Ecommerce, R800/mo | 20 with CMS | 6 to 10 weeks | Product data, categories, payments |
Techadon packages and typical build timelines
Frequently asked questions
Techadon builds and hosts websites for businesses across South Africa from our office at 173 Oxford Road, Rosebank, Johannesburg. Packages start at R300 a month. See the published prices or ask a question.


